projects

THIVA'S COURTHOUSE

Location GREECE, THIVA
Client PERFECTURE OF THIVA
Contractor EKTER S.A.
Participation 100%
Construction Period 12/1992-12/1997
Project value 8,779,000.00

Description

The courthouse was designed and constructed in order to satisfy the judicial court needs of Thiva's urban area.
Technical Data:

  • Building Construction area:  8.000 m2
  • Pile Foundation and Diaphragms
  • Roofing:  sheets of Titanium zinc
  • Substation of Medium Voltage:  1.600 kVA
  • Air conditioning:  250 tons of cooling capacity
  • Spatial heating:  400 Mcal/h heating power
  • Building insulation
  • Waterproofing protection