NEW COLD SMS ROLLER - ELVAL PLANT

Location GREECE, INOFITA VIOTIAS
Client ELVAL SA
Contractor EKTER S.A.
Participation 100%
Construction Period 12/1999-12/2000
Project value 3,188,000.00

Description

The project consists of the construction of a new Cold SMS Roller at the Elval Plant.
Technical Data:

  • Reinforced concrete volume:  17.768 m3
  • Exposed concrete formwork:  8.073 m3
  • Construction of industrial floors covering:  1.394 m²
  • Drilling of Φ1000 boreholes: 1.200 m piles
  • Construction of exposed coating:  4.990 m²
  • Glazing construction of total area:  155 m²
  • Construction of suspended ceiling area:  463 m²
  • Construction of plaster partition area:  599 m²
  • Installation of ceramic tiles:  584 m²
  • Installation of building's electrical system
  • Installation of building's hydraulic system
  • Installation of building's fire detection system